Week 31- 33 Shower screens, Tapware, Flooring

We are nearly there. It is small things now.  As we entered the house for the next set of things happening we noticed that all the tapware was in place.  Also, the flooring wrt tiles and carpet had been done. The second coat of paint had started. We had chosen a different shade of paint... Continue Reading →

Week 20-21 Prelining and Gyprock

We had Pre-lining inspections around Week19 and the report had arrived with a few defects.Some walls required straightening, balcony posts were not installed, lower gutter was not installed. We spoke to our Supervisor about it and he set aside dates to work on them. The Week 20 was when Gyprock was to be installed. We... Continue Reading →

Week 13-15 Roof and Eaves

    As we progressed to Week 13 the upper level bricks were completed.  We also saw that the  upper Roof was installed . The structure of the house was all coming together. We also got acid wash for the upper level of bricks.The eaves for the upper roof had also been painted. The balcony... Continue Reading →

Week 4-6 Frames

Frames had been delivered at the end of Week 3. By week 4 we were happy to see some progress on the ground floor frames. Another week had gone by and the frames were going up pretty quickly. We saw some scaffolding onsite as well We also found our neighboring site was fenced and excavated... Continue Reading →

Week 0-1 Construction begins with Slab

We had finally left the admin behind. Bank approval came though and our LACC had arrived.It was time for our file to move to production estimating. The site was cleared and toilet installed. We had a Eureka moment looking at the below site(sight) 🙂   Once the site was cleared it was time for the... Continue Reading →