TimeLine

Our Dates/TimeLine
18/04/2017 Initial deposit
29/05/2017 Date of Tender
29/06/2017
Consolidated Tender acceptance
05/07/2017 Revised Tender Request
13/07/2017 Revised Tender arrived
19/07/2017
Revised Tender accepted
23/08/2017
Plan Drawings not yet arrived
06/10/2017 Final Plan for contracts
12/10/2017 Contract Signed
14/11/2017 Appointments
05/12/2017 DA lodged
22/12/2017 DA approved
25/1/2018 Draft End Pane,
13/02/2018 Construction plans
22/02/2018 Loan approval
07/03/2018 LACC
09/03/2018 Site Cleaning
16/03/2018
File moved to Production Estimating
09/04/2018
File moved to Construction
10/04/2018 Piering Done
14/04/2018 Slab done Week0
April16 invoice Slab
09/05/2018 Frames Started Week4
25/05/2018 Frames completed Week6
May25 invoice Frames and roof trusses
07/06/2018 Bricks start Week8
08/07/2018 Bricks end date Week12
13/07/2018 Roof installed Week13
July13 – invoice Brickwork
20/07/2018 Eaves and washing Week 14
27/07/2018 Rough Ins Week 15
03/08/2018 Rough Ins Week 16
10/08/2018 Lower Roof and Eaves Week 17
17/08/2018 No progres Week 18
25/08/2018 Pre Lining and Insulation Week 19
30/08/2018 Gyprock Week 20
07/09/2018 Waterproofing Week 21
14/09/2018 Waterproofing Week 22
21/09/2018 Kitchen Week 23
This week was supposed to be stairs but due to supervisor not following up with stairs they did not arrive. Other works are dependent on stairs
28/09/2018 Stairs and Doors Week 24 and 25
11/10/2018 Paint and CounterTops Week 26 Tiles delayed
18/10/2018 BathRoom Tiles Week 27
25/10/2018 Flooring Week 28
1/11/2018 Plumbing and electrical Week 29
7/11/2018 Plumbing and electrical Week 30
14/11/2018 Small finishes and carpentry Week 31
21/11/2018 Shower screens and tapware Week 32
28/11/2018 Paint ,Mirrors and finishing of Doors Week 33
7/12/2018 Driveway Week 34
12/12/2018 Porch and alfresco roof Week 35
17/01/2018
Area construction Manager Approval
25/01/2018
PCI and Private Inspection
14/02/2018 Keys

 