Week 31- 33 Shower screens, Tapware, Flooring

We are nearly there. It is small things now.  As we entered the house for the next set of things happening we noticed that all the tapware was in place.  Also, the flooring wrt tiles and carpet had been done. The second coat of paint had started. We had chosen a different shade of paint... Continue Reading →

Week 20-21 Prelining and Gyprock

We had Pre-lining inspections around Week19 and the report had arrived with a few defects.Some walls required straightening, balcony posts were not installed, lower gutter was not installed. We spoke to our Supervisor about it and he set aside dates to work on them. The Week 20 was when Gyprock was to be installed. We... Continue Reading →

Selections : Day 1 – Tiles-Di Lorenzo

I was a overload of some really helpful information from the forums (forum.homeone) and a few other bloggers who were building with W. Almost everyone advised us to do a lot of homework and preparation prior to the selections. We had already selected our brick Vino ( as mentioned in my previous posts) and also... Continue Reading →

Dream Home Journey- The beginning ..

Real estate prices in Sydney were already sky rocketting. Here we were like most of the first timers in the house market ,waiting for things to settle down or saturate. However having observed for a couple of years we decided things may not be changing much. Also we were paying someone else's mortgage. Instead we... Continue Reading →