Week 31- 33 Shower screens, Tapware, Flooring

We are nearly there. It is small things now.  As we entered the house for the next set of things happening we noticed that all the tapware was in place.  Also, the flooring wrt tiles and carpet had been done. The second coat of paint had started. We had chosen a different shade of paint... Continue Reading →

Week 20-21 Prelining and Gyprock

We had Pre-lining inspections around Week19 and the report had arrived with a few defects.Some walls required straightening, balcony posts were not installed, lower gutter was not installed. We spoke to our Supervisor about it and he set aside dates to work on them. The Week 20 was when Gyprock was to be installed. We... Continue Reading →

Selections : Day-1-Kitchen

Once the tiles were done we sped to an Aircon appointment with Ultra Air which finished fairly quickly. At the end of it we had upgraded to the ESP Plus module with 5 zones and a Wi-Fi based controller which cost us approx $5k. We had no time for lunch and had to do with ... Continue Reading →

Proudly powered by WordPress | Theme: Baskerville 2 by Anders Noren.

Up ↑