We are nearly there. It is small things now. As we entered the house for the next set of things happening we noticed that all the tapware was in place. Also, the flooring wrt tiles and carpet had been done. The second coat of paint had started. We had chosen a different shade of paint... Continue Reading →
Week 22-23 WaterProofing and Kitchen Cabinetry
Week 22 we had a call from the Supervisor updating that the waterproofing had been done and they were waiting on the stairs for the rest of the work to be commenced. Later on he called once again stating owing to the supervisor changes there was no communication initiated with the Stairs suppliers . 😐 ... Continue Reading →
Week 2-3 Slab curing and external plumbing
The slab was left to be cured for a couple of weeks. Also the external plumbing work was carried out. We got a progress payment claim invoice for the slab to be sent to the bank .We received a call from the landscapers for a quote for removal of the soil and leveling the land... Continue Reading →