Our Dates/TimeLine
|
|||
18/04/2017 | Initial deposit | ||
29/05/2017 | Date of Tender | ||
29/06/2017 |
Consolidated Tender acceptance
|
||
05/07/2017 | Revised Tender Request | ||
13/07/2017 | Revised Tender arrived | ||
19/07/2017 |
Revised Tender accepted
|
||
23/08/2017 |
Plan Drawings not yet arrived
|
||
06/10/2017 | Final Plan for contracts | ||
12/10/2017 | Contract Signed | ||
14/11/2017 | Appointments | ||
05/12/2017 | DA lodged | ||
22/12/2017 | DA approved | ||
25/1/2018 | Draft End Pane, | ||
13/02/2018 | Construction plans | ||
22/02/2018 | Loan approval | ||
07/03/2018 | LACC | ||
09/03/2018 | Site Cleaning | ||
16/03/2018 |
File moved to Production Estimating
|
||
09/04/2018 |
File moved to Construction
|
||
10/04/2018 | Piering Done | ||
14/04/2018 | Slab done | Week0 |
April16 invoice Slab
|
09/05/2018 | Frames Started | Week4 | |
25/05/2018 | Frames completed | Week6 |
May25 invoice Frames and roof trusses
|
07/06/2018 | Bricks start | Week8 | |
08/07/2018 | Bricks end date | Week12 | |
13/07/2018 | Roof installed | Week13 |
July13 – invoice Brickwork
|
20/07/2018 | Eaves and washing | Week 14 | |
27/07/2018 | Rough Ins | Week 15 | |
03/08/2018 | Rough Ins | Week 16 | |
10/08/2018 | Lower Roof and Eaves | Week 17 | |
17/08/2018 | No progres | Week 18 | |
25/08/2018 | Pre Lining and Insulation | Week 19 | |
30/08/2018 | Gyprock | Week 20 | |
07/09/2018 | Waterproofing | Week 21 | |
14/09/2018 | Waterproofing | Week 22 | |
21/09/2018 | Kitchen | Week 23 |
This week was supposed to be stairs but due to supervisor not following up with stairs they did not arrive. Other works are dependent on stairs
|
28/09/2018 | Stairs and Doors | Week 24 and 25 | |
11/10/2018 | Paint and CounterTops | Week 26 | Tiles delayed |
18/10/2018 | BathRoom Tiles | Week 27 | |
25/10/2018 | Flooring | Week 28 | |
1/11/2018 | Plumbing and electrical | Week 29 | |
7/11/2018 | Plumbing and electrical | Week 30 | |
14/11/2018 | Small finishes and carpentry | Week 31 | |
21/11/2018 | Shower screens and tapware | Week 32 | |
28/11/2018 | Paint ,Mirrors and finishing of Doors | Week 33 | |
7/12/2018 | Driveway | Week 34 | |
12/12/2018 | Porch and alfresco roof | Week 35 | |
17/01/2018 |
Area construction Manager Approval
|
||
25/01/2018 |
PCI and Private Inspection
|
||
14/02/2018 | Keys |